"Fast & efficient, innovative & practical, green & environmental protection, win-win cooperation" is the enterprise cultural core of Speed Technology. To"Manufacturing the most reliable network equipment" for our own mission, to " 1+1 is greater than 3" of our win-win mode, providing the customers with more valuable ways of cooperation.To the future needs of users for research and development objectives, providing our clients with latest network equipment and satisfactory service.

Switch installation guide

UKG2400GC Installation Guidance

File size:M

Products configuration table
Before installing switch, please check if the product package has the following parts:
  ★ A switch
  Bracket Accessory (19&rsquo rack)
  Product operation manuals
  AC power cord
Setting up switch
   Install the switch and mounting accessories
   Powered on
   Connect with the switch and the PC terminal
   Factory default settings are as follows:
     Set IP address:192.168.1.3
     Subnet mask :255.255.0.0
     Default gateway:192.168.1.1
     Initial users:admin
     Initial password:none
note:
    In the terminal PC to connect switches setting, ensuring the PC's IP address belongs to 192.168.1 network segment, and set IP address as the any IP among 192.168.1.2~192.168.1.254(not include 192.168.1.3), so it can properly access the settings page of this switch.
Recovery factory set:
    While the switch is powered up, press the reset switch on upper left corner of the front panel of the switch, lasts for 6 seconds, you can restore the factory settings.
Preparatory work:
    The switch needs to installed in a well-ventilated environment. Be sure to have a good ventilation, and set aside around 100 mm (4 inches) of space.
The switch installed in 19 inches standard rack:
    Each switch provides a set of ears, which is used to install the router in a 19-inch rack.  Each set of ear piece includes two ear pieces and six screws.
    Step 1: Fixes the ear piece on switch by screw.
    Step 2: Place switch into 19 inches of the rack, and confirm that there is adequate ventilation distances.
    Step 3: Ear pieces are locked on the rack by screw.
The switch installed on the wall:
    Step 1:Fixes the ear piece on switch by screw.
    Step 2: Using 5/8 inch 12 wood screws (not to provide) fixes the ear piece on the wall.
The switch installed in your desktop:
There are four rubber pad on the switch package. These rubber pads can help prevent the router from desktop slide.
    Step 1: Open the sticker on the back of rubber pad .  
    Step 2: The rubber pad paste firmly at the bottom of the switch.
    Step 3: The switch is placed in a flat position
The switch connected to AC power:
    In the package of the switch, there is a power cord in comply with international common power socket specifications. If you find the specifications of the power cord is incorrect, please contact your local dealer to replace.
    Step 1: The female-head end of the power cord is inserted into main power socket located in the switch panel. Then the other end is connected to an AC power.
   Step 2: Once switches access the ac power, switches will start work at once.


 